Carnegie Renovations Project
Overview
The Carlynton School District is excited to share progress on the upcoming Carnegie Elementary School Renovation Project, a major investment in the future of our students, staff, and community. The project will modernize classrooms, enhance safety and accessibility, and create new learning spaces to support 21st-century education.
A key highlight of the renovation is the construction of a new cafetorium addition at the rear of the building. This multi-purpose space will serve as a cafeteria, auditorium, and community event center, providing students and residents with a flexible gathering area for school assemblies, performances, and local events. The cafetorium will also include additional restrooms to support community use during stadium events, improving accessibility and convenience for all visitors.
Construction is scheduled to begin in May 2026 and conclude by July 2027, transforming the Carnegie Elementary campus while maintaining a focus on student safety and continuity of learning.
| Milestone | Date / Timeframe | Description |
|---|---|---|
| Project Out to Bid | September 17, 2025 | Bid documents released to contractors. |
| Pre-Bid Meeting Held | September 25, 2025, 3:30 PM | Meeting held at Carnegie Elementary with prospective contractors to review project details and site conditions. |
| Bids Due | October 21, 2025 | Extended bid period to allow contractors additional time for review and submission. |
| Bid Review | November 11, 2025 | Bid evaluations presented to the Board during the Work Session. |
| Contract Award | November 18, 2025 | Board consideration and approval of construction contracts. |
| Notice to Proceed | November 21, 2025 | Official authorization for contractors to begin project planning. |
| Contractor Submittals | January – May 2026 | Detailed planning, scheduling, and coordination by selected contractors. |
| Construction Period | May 25, 2026 – July 30, 2027 |
On-site construction and phased renovations. |
In the event of construction delays, the District may consider a post-Labor Day start to the 2027–2028 school year if necessary.
Phased Construction Plan
To minimize disruption and maintain a safe environment, construction will occur in five major phases:
- Phase One – Auditorium Alterations (May 2026)
- Phase Two – Summer 2026
- Phase Three – Addition (June 2026 – July 2027)
- Phase Four – Lower Level Alterations (Late December 2026)
- Phase Five – Summer 2027
Phase One – Auditorium Alterations (May 2026)
Phase Two – Summer 2026
Phase Three – Addition (June 2026 – July 2027)
Phase Four – Lower Level Alterations (Late December 2026)
Phase Five – Summer 2027
Project Updates
As the project progresses, the District will post regular updates, photos, and notices to this page to keep families and community members informed.
Updates will include:
-
Construction progress photos
-
Key milestones reached
-
Any schedule adjustments
-
Community impact notices (parking, access, etc.)
Contact
For questions regarding the Carnegie Elementary Renovation Project, please contact:
Dr. John Kreider, Superintendent
john.kreider@carlynton.k12.pa.
Mr. Al Pater, Director of Facilities and Maintenance
albert.pater@carlynton.k12.pa.